A traveling grate furnace is a periodic operation furnace, and mastering the correct operation method is crucial. It is of great significance in reducing equipment failure rates, improving heating efficiency, and extending the service life of the equipment. Today, we, as a traveling grate furnace manufacturer, will explain the operation procedures and precautions for using the traveling grate furnace.
One, Operation Procedure for Trolley Furnace
1. Pre-operation inspection for the trolley furnace
Employees undergo training to understand safety operation standards, familiarize themselves with the construction and performance of the trolley furnace, and must pass the department's assessment before they can start working.
Before each operation, inspect the appearance of the trolley furnace for any visible defects that may affect its normal operation. If any damage is found, repair it immediately before use.
Prior to operating the control car furnace, check that all control lines and the wiring of each heating component are properly connected according to specifications, ensure good contact conditions, and identify any instances of poor contact.
④ Inspect the smoothness and ease of the furnace door hinge and the lower bearing wheel, and ensure the pressure mechanism of the furnace door is light and flexible, safe, and reliable.
Check the seal integrity of the furnace body and door panels to ensure they meet the requirements and maintain good sealing.
Ensure the trolley furnace is free of errors before beginning work, and strictly prohibit any over-limit operations. The shell height must not exceed 70cm, and the width must not exceed 100cm.
2. Trolley furnace operation process
After the workpiece is assembled, close the furnace door, check for sealing, then activate the main heating circuit and wait for the furnace to heat up. After a period of time, inspect the temperature around the equipment. If there is any overheating or abnormal phenomena, stop the operation immediately and conduct repairs.
Before removing the workpiece from the furnace, the power supply to the main heating circuit should be disconnected first, and then the furnace door can be opened to perform the removal operation.
Once the furnace reaches a certain temperature, it can be maintained. During this process, the temperature controller and the maintenance of the insulation should be monitored. After reaching the specified insulation time, the furnace door can be opened, and the workpieces inside can be sent out.
After completing the aforementioned steps, close the furnace door, adjust all controllers to zero, and turn off the main power. Clean the surrounding environment and hygiene of the trolley furnace, and check for any abnormal areas on the furnace body.
Section II: Safety Precautions for Trolley Furnace Operation
During the operation of the trolley furnace, operators must not leave their posts at will and should always monitor the working status of the trolley furnace.
2. Operators should be familiar with the standard positions of the buttons on each switch box and adhere to the instructions manual. Pay attention to electrical usage to prevent short circuits or other electrical malfunctions caused by improper use, which could severely compromise personal safety.
3. Adhere strictly to the trolley furnace operation procedures, strictly prohibit exceeding the limit of work, and strictly prohibit use within the heating zone. The workpiece should maintain a certain distance from the electric heating device and the rear wall.
4. No corrosive, volatile, or explosive gases are permitted in the workpieces entering the furnace for processing. Otherwise, it may affect the service life of the heating elements and refractory materials, and easily lead to accidents such as explosions.
5. Newly installed or heavily repaired electric furnaces must undergo baking in accordance with regulations, followed by a trial run to ensure there are no issues before they can be used further.
6. The work site should be kept clean, free from any debris that could affect operations, and the furnace area should be cleared after completion.
Prohibit operations with live electricity and粗暴 handling of parts to prevent damage to the parts and furnace.
During the operation of the furnace door, do not approach moving parts to avoid scratches or burns.
The workpiece must not come into contact with the heating element, and the spacing between the workpiece and the heating element should be between 100 to 150 mm.
Regular inspections and calibrations of instruments and electric heaters should be conducted, and any anomalies found should be repaired immediately.
To ensure the personal safety of operators, the trolley furnace should first disconnect the power supply to the heating components before loading or unloading workpieces.
Chamber oxidation layers, including resistive wires or strips, should be cleaned at least once a week. Compressed air can be used for blowing at the bottom of the furnace.
13. Disconnecting the wiring protection cover is strictly prohibited except during maintenance. Prior to maintenance, the main switch must be turned off and warning signs should be properly placed. After maintenance, the wiring protection cover must be reinstalled and its protective function must be ensured.
Here is the operation procedure and precautions for the trolley furnace. We hope it is helpful to you! The high-temperature muffle furnaces produced by Luoyang Xingding Kiln Co., Ltd. are easy to use, come in various specifications, and guaranteed in quality. If you need any information, please feel free to call for consultation.
Disclaimer:Images and text on this site are collected and compiled from the internet for learning and exchange purposes only, and are the property of their respective owners. They do not represent the views of our site. We will not assume any legal liability. If any of your rights are infringed upon, please contact us promptly for removal.