How to Establish a Mobile Fuel Station? Luqiang Energy Equipment Co., Ltd. is here to inform you that a mobile fuel station is an on-site fueling equipment that integrates ground fireproof and explosion-proof storage tanks, fuel dispensers, and automatic fire extinguishers. It features fireproof and explosion-proof capabilities, safety and environmental protection, small land area requirements, and ease of relocation. If you are interested in operating this project, what procedures do you need to follow? Mobile stations are categorized into two types: those for internal corporate use and those for commercial operations, with different procedures required.
One: Process for handling operational手续 procedures for portable unit stations.
1. Site Selection (in compliance with gas station and refueling station standards)
2. Apply to the Planning Bureau for the land use permit for a gas station at the specified location.
3. Visit the Land Bureau to handle the land commercial transfer procedures.
4. Simultaneously, handle the approval documents for the newly established skid-mounted gas station at the Bureau of Commerce.
5. Apply for a Fire Prevention Site Selection Opinion Letter at the Fire Department
6. Commissioned a petrochemical qualification design institute to produce design drawings and safety and fire prevention special sections.
7. Commissioned a safety evaluation company to produce a safety evaluation report
8. Completed the "Three Simultaneity" procedures at the Safety Administration Bureau
Engage an environmental assessment company to produce an environmental impact assessment report
10. Submitted architectural drawings for review to the Construction Committee and obtained a construction permit.
11. Commissioned a qualified petrochemical installation unit to construct a skid-mounted fuel station.
Fire and Safety Supervision Bureau Inspection
13. Apply for a finished product business license at the Commerce Bureau
14. Completed the registration of mobile fuel stations with industry and commerce, taxation, quality supervision, and banks.
Two: Handling of on-site mobile fuel station procedures for internal corporate use:
1. Selected an internal site for the company (a location that complies with the safe distance for the placement of skid-mounted equipment)
2. The company has sent two or more employees to attend safety operation training and certification at the Safety Supervision Bureau.
3. Commissioned a design institute with petrochemical qualifications to conduct the design.
4. Hired a safety evaluation company to produce a safety evaluation report
5. File with the Safety and Fire Supervision Bureau