The operation process of the automatic warp threading machine mainly includes the following steps:
1. Equipment Preparation: Includes overall frame connection, steel comb carding of the yarn layer, and yarn frame lifting to the middle position.
2. Drawing Process and Yarn Type Configuration: Set equipment specifications, initiate parameter settings, and position each module, then begin the drawing process.
3. Yarn Drawing: Prepare the yarn on the yarn frame, then draw the yarn, including threading the heald and removing the steel box from the equipment.
4. Inspection and Adjustment: Remove the pipettes, frames, steel boxes, and other components from the equipment to ensure everything is in place.