Installation Method and Requirements for Outdoor Camera Pole for Television Surveillance
Arm length should be determined based on the actual site conditions.
Detailed elaboration of specific process requirements.
1. Basic Construction
1.1. Foundation Piling
Purpose: Fixed camera pole.
B. Infrastructure, dimensions: As shown in the figure.
Base Model: Determined by the required fixed camera pole model.
Foundation to be constructed at the camera pole location marked on the "Equipment Layout Plan."
E. Production Requirements: 1. Must comply with the current national standard "Cable Line Construction and Acceptance Code for Electrical Installation Engineering."
In accordance with the provisions of "Regulations of Fan."
Between the foundation and the manhole, there should be a conduit for wiring and iron wire should be placed inside.
3. Reinforcing steel on the basic steel plate is threaded to M20 standards, accompanied by two galvanized screws, a flat washer, and
One spring washer each.
Materials: 8mm steel plate, 20mm steel bar, C25 concrete, gravel, 2.5-inch PVVC elbow pipe.
1.2. Manhole Manufacturing
Purpose: Facilitates cable laying and system detection and maintenance.
B. Infrastructure, Dimensions: As shown in the figure. The depth, height, and width of the well are indicated in the image.
Other sizes are determined by the contractor based on the on-site conditions.
C. Production Location: As marked on the "Equipment Layout Plan," produce at the designated manhole location.
D. Production Requirements: 1. Shall comply with the current national standard "Code for Construction and Acceptance of Cable Lines for Electrical Installation Engineering."
Please comply with the provisions of "Regulations of Fan."
2. The manhole has excellent sealing and waterproof performance.
Steel plate σ=8
800
800
Ф230
Ф400
Φ320
1600 1700
100
Rubble
C25 Concrete
Materials: bricks, cement, steel plates.
Cable conduit installation
Purpose: Laying cables, preventing cable damage.
B. Pipeline Routing: Install exposed and concealed pipelines according to the types and routes indicated in the "Equipment Layout Plan." Note the diagram...
The specified pipe diameter;
C. Production Requirements: 1. Shall comply with the current national standard "Cable Line Construction and Acceptance Code for Electrical Installation Projects"
As stipulated by the relevant provisions of "Regulations of Fan."
2. The cable conduit is well-sealed, offering excellent waterproof performance.
Cable conduit should be no less than 0.7 meters from the ground.
Cable conduit openings should be free of burrs and sharp edges.
5. Wire rope is placed inside the cable conduit.
Materials: 1. Buried pipe installations use steel pipes.
Manhole Covers (Steel)
250
350
Clay manholes are lined with bricks and stones.
Piping Lines
Manhole Cover (Steel)
600
Manhole structure diagram
2. The installation uses PVC pipes.
1.4. Grounding Installation
Purpose: To prevent external voltage from endangering personal safety and damaging equipment, suppress electrical interference, and ensure proper operation of the equipment.
Our team consistently works diligently.
B. Grounding Body Structure and Dimensions: As shown in the "Illustration of Grounding Body Structure."
Installation Location: Install the grounding body according to the marking on the "Equipment Layout Plan." Drawing Number: ;
Installation Requirements: 1. Shall comply with the current national standard "Cable Line Construction and Acceptance Code for Electrical Installation Engineering."
Pursuant to the provisions of "Regulations of Fan."
2. The grounding body should be welded using a lap weld, with the lap length being six times the diameter of the round steel.
3. The grounding body installation point should have no pipes or cables running beneath it.
4. The installation depth of the grounding body is as shown in the "Grounding Body Installation Diagram."
5. After the grounding body is installed, the grounding resistance should be measured using a grounding ohmmeter, with the requirement that the grounding resistance be within the specified range.
The ground resistance is less than 4Ω. Note that resistance should not be measured immediately after rain.
Material: 2.5-inch steel pipe and 30*5 flat steel.
2. Piling Fabrication and Installation
2.1. Pole Fabrication and Installation
Application: For installing camera tripods.
B. Camera pole structure and dimensions: See "Camera Pole Diagram."
Earth Rod Structure Diagram
Φ10
700
1500
300
2200
Ground
Soil
Installation of Grounding Body Schematic
C. Production Requirements: See text description in "Camera Pole Diagram."
Installation Method: Secured through foundation bolts and camera pole base connection, as shown in the "Camera Pole Installation Scenario Diagram."
F. Installation Tools: Wrench
G. Installation Requirements: 1. Secure installation.
The centerline of the camera boom should be perpendicular to the horizontal plane.
The center line of the two oval holes on the camera pole, positioned at a 180-degree angle, should be parallel to the direction of the road.
4. A wire for threading the cable is placed between the manhole at the base of the camera pole and the various waist-shaped holes.
Camera Mount Production and Installation
Purpose: Installation of camera rain cover.
B. Structure: See "Camera Tripod Diagram."
C. Dimensions: See the Camera Tripod Diagram.
D. Production Requirements: Refer to the text descriptions in the "Camera Tripod Diagram."
Installation Method: Secure the tripod component 1 to the camera pole using a clamp, as shown in the "Camera Tripod Installation Diagram."
F. Installation Tools: adjustable wrench, ladder, or lift truck.
No Chinese content provided for translation.
Lane
Green Belt
Camera Boom
Camera Boom Centerline
Perpendicular to the horizontal plane
Waist-shaped holes, totaling six
The centerline of the waist-shaped hole at an angle of 180 degrees should align with the road alignment.
Please forward.
Wire Twisting
Illustration of Camera Pole Installation Scenario
G. Installation Requirements: 1. Secure installation.
2. For component 1 of the camera tripod, the wiring hole should align directly with the waist-shaped hole of the camera rod.
Requirements for civil construction and installation of upright poles
Bidder shall conduct on-site measurement of technical data for the purpose of estimating the project volume.
2. Cable burial trench dimensions: Sidewalk - 0.2m x 0.6m (width x depth), Roadway - 0.2m
0.8 meters (width x depth). The bottom of the trench is initially lined with a C20 concrete layer, followed by the cable laying, and then backfilled with fine sand.
Reinforce, then restore the road surface according to actual conditions.
3. The cables laid are protected with PVC pipes, except for those buried in flower beds or otherwise specified.
Protected with galvanized steel pipes; all exposed cables (excluding overhead) are made of galvanized material.
Steel pipes are protected.
4. Description: Source and Contact Information: