1. Construction layout is conducted based on the flat position, elevation, and geometric dimensions as designed by the drawings.
Extend and secure the excavation control pile 2 meters out of the excavation pit.
Ensure proper drainage during excavation and set up a sedimentation well outside the foundation pit to facilitate basement drainage.
4. Excavate down to the medium sand layer, clear the upper fill soil, and then backfill with coarse sand to the base elevation.
After excavation of the foundation pit, the bearing capacity of the basement should be inspected. If the bearing capacity does not meet the requirements, it should be handled according to the supervisor's instructions.
During the excavation process of the foundation pit, any leakage in the retaining structure must be sealed promptly.
Integrated prefabricated pumping stations are pressurized pumping stations designed for lifting sewage, rainwater, drinking water, and waste water. They are produced and assembled in a factory before being transported to the site for installation.